Moving office means rebuilding the IT from scratch. Planned well it goes unnoticed; planned badly it drags on for weeks. Order matters.
This is the most critical item and the one that most often slips. Getting a business line to a new address can take weeks if the building has no infrastructure.
If you are considering a second line for resilience, make sure it uses different infrastructure.
On the floor plan of the new office, establish:
Install more outlets than you need today. Adding cable later costs several times what it costs during the fit-out. It must be done before decorating and furniture.
Requirements for the cabinet location:
These four are the hardest things to correct afterwards. We have seen plenty of offices with the cabinet inside a kitchen unit, running hot for years.
1. Network infrastructure first: cabinet, switching and access points installed and tested
2. Then the servers: installed, powered on, services verified
3. User machines last
The reverse order is the common mistake. Computers are placed on desks, then it emerges the network is not ready and everyone waits.
When moving servers, take care: disks are sensitive to shock. Rack servers should travel upright and secured, not flat.
The last item gets skipped, and six months later nobody knows which cable goes where.
Ask us about network infrastructure and cabling, or request a free assessment directly.
Buying better access points fixes it about a third of the time. Here is what the rest of the time looks like.
Sometimes the honest answer is no. Here is how to tell which case you are in.
The model number goes up and so does the price. But which one does your office actually need?